CERC Hearing: Implications for PGCIL Transmission Projects

CERC Hearing: Implications for PGCIL Transmission Projects

POLICY & REGULATIONS

Case Summary – PGCIL Transmission Tariff Petitions

  • Forum: Central Electricity Regulatory Commission (CERC), New Delhi
  • Date of Hearing: 26 August 2025
  • Coram:
    • Jishnu Barua, Chairperson
    • Ramesh Babu V., Member
    • Harish Dudani, Member
    • Ravinder Singh Dhillon, Member

1. Petitions Covered

  1. 212/TT/2024 – Tariff (COD–31.03.2024) for 7 assets under Provision of Spare ICTs, Northern Region.
  2. 284/TT/2024 – Tariff (COD–31.03.2024) for 7 assets under Scheme to Control Fault Level (Phase-II), Northern Region.
  3. 408/TT/2024 – Tariff (COD–31.03.2024) for 10 assets under Eastern Region Strengthening Scheme-XVII (Part-B) (ERSS-XVII Part-B).
  4. 446/TT/2024 – Tariff (COD–31.03.2024) for 500 MVAr Thyristor Controlled Reactor (TCR) at Kurukshetra.
  5. 59/TT/2025 – Tariff (2019–24) for 9 assets under Strengthening of OPGW Network within ER Grid and Connectivity with Other Regions.
  6. 262/TT/2025 – Tariff (2019–24) for 765 kV 80 MVAR Single Phase Reactor at Bilaspur Substation under ERPC/WRPC recommendations.

2. Parties

  • Petitioner: Power Grid Corporation of India Ltd. (PGCIL)
  • Respondents: State DISCOMs/utilities (UPPCL, BSPHCL, MP Power Management Co. Ltd., etc.).
  • Appearance: Only BSPHCL appeared (in Petition 408/TT/2024).

3. Submissions

  • PGCIL: Stated that all required information has been filed; pleadings complete; sought approval of tariff as claimed.
  • Respondents: Mostly absent, except BSPHCL which participated in one petition.

4. Commission’s Directions

General

  • Last opportunity for respondents to file replies within 2 weeks (copy to PGCIL).
  • PGCIL may file rejoinders within 2 weeks thereafter.
  • PGCIL to submit additional clarifications by affidavit within 2 weeks.

Petition-Specific

  • 212/TT/2024: Explain delays (5–21 months) in supply of materials for Assets 5, 6, 7.
  • 284/TT/2024: Provide asset-wise shutdown overrun details (required vs. approved timelines).
  • 408/TT/2024: Justify time overruns (activity-wise: RoW, shutdowns) and submit CEA energization & trial-run certificates for Assets 1A, 5, 8.
  • 59/TT/2025: Furnish pending information as sought in earlier RoP (20.06.2025).

5. Outcome

  • Nature of Order: Procedural (Record of Proceedings).
  • Effect: Replies, rejoinders, and clarifications mandated before final decision.
  • Status: Subject to compliance, orders reserved in all six petitions.