Case Summary – PGCIL Transmission Tariff Petitions
Forum: Central Electricity Regulatory Commission (CERC), New Delhi
Date of Hearing: 19 August 2025
Coram:
- Jishnu Barua, Chairperson
- Ramesh Babu V., Member
- Harish Dudani, Member
- Ravinder Singh Dhillon, Member
1. Petitions Covered
- 396/TT/2024 – Tariff for assets under Eastern Region Strengthening Scheme – XXII (ERSS-XXII).
- 211/TT/2024 – Tariff for 4 assets under North East–Northern/Western Interconnector-I Project (NER).
- 213/TT/2024 – Tariff for 1 no. 220 kV line bay at Chamera Pooling Station (for Karian–Chamera Pool line, NR).
- 196/TT/2025 – Truing up (2019–24) & tariff for 2024–29 for:
- Asset-I: 50 MVAR Line Reactor at Jaipur (South) (used as Bus Reactor).
- Asset-II: 400 kV D/c Kota–Jaipur (South) line with bays (RAPP 7&8 evacuation, NR).
2. Parties
Petitioner: Power Grid Corporation of India Ltd. (PGCIL)
Respondents: State utilities (BSPHCL, APDCL, HPPTCL, UPPCL, etc.)
Other Participants: NHPC, NPCIL
3. Proceedings
- 396/TT/2024: PGCIL sought permission to implead WBSETCL as party; Commission allowed, directed amended Memo of Parties.
- 196/TT/2025: Respondent counsel sought adjournment (illness).
- 211/TT/2024 & 213/TT/2024: Counsels flagged mismatch in implementation of assets; requested further listing.
4. Commission’s Directions
General:
- Petitioner to file required data/information within 2 weeks (affidavit).
- Respondents to file replies within 2 weeks; Petitioner may file rejoinder within 1 week.
Petition-specific:
- 396/TT/2024: Submit Form-5A & Part-B of Form-7.
- 211/TT/2024:
- Justify delay in forest clearance (2012 rejection → 2018 reapplication).
- Submit Part-B of Form-7.
- Confirm recovery of LD from contractor (details).
- Provide award/commencement/completion dates.
- Activity-wise time overrun table (with reasons).
- RoW overrun details with evidence of compensation.
- Shutdown overrun details.
- Confirm commissioning “on load”.
- Submit updated Auditor’s Certificate & IDC discharge statement reflecting revised notional IDC (₹12,276.26 lakh for Asset-2; ₹15,056.27 lakh for Asset-3).
- Reconcile IDC figure mismatches between petition & computations.
- 213/TT/2024:
- Justify LOA completion mismatch (planned 24.04.2022 vs. actual 27.04.2022) with supporting docs.
- Provide CTUIL Certificate (per Grid Code 2023, Reg. 27(1)(c)) approving COD.
5. Next Hearing
Scheduled for 21 October 2025.
6. Outcome
Type of Order: Procedural (Record of Proceedings)
Effect: Multiple compliances ordered (IDC reconciliation, RoW/shutdown data, CTUIL certification, amended parties).
Final tariff determination reserved, pending compliance.