Petition Submitted for Transmission Tariff Determination of COD Assets under Spare ICTs in Northern Region

Petition Submitted for Transmission Tariff Determination of COD Assets under Spare ICTs in Northern Region

POLICY & REGULATIONS

Case Summary – PGCIL Tariff Petitions (Spare ICTs, Fault Level Control, ERSS-XVII, Kurukshetra TCR, OPGW Strengthening, Bilaspur Reactor)

Forum: Central Electricity Regulatory Commission (CERC), New Delhi
Date of Hearing: 26 August 2025

Coram:

  • Jishnu Barua, Chairperson
  • Ramesh Babu V., Member
  • Harish Dudani, Member
  • Ravinder Singh Dhillon, Member

Petitions Covered

  • 212/TT/2024 – Tariff (COD to 31.03.2024) for 7 assets under Provision of Spare ICTs in NR
  • 284/TT/2024 – Tariff (COD to 31.03.2024) for 7 assets under Scheme to control Fault level (Phase-II) in NR
  • 408/TT/2024 – Tariff (COD to 31.03.2024) for 10 assets under ERSS-XVII (Part-B) in ER
  • 446/TT/2024 – Tariff (COD to 31.03.2024) for 500 MVAr Thyristor Controlled Reactor at Kurukshetra (NR)
  • 59/TT/2025 – Tariff (2019–24) for 9 assets under Strengthening of OPGW network within ER Grid
  • 262/TT/2025 – Tariff (2019–24) for 80 MVAR Reactor at Bilaspur Substation (ERPC & WRPC recommendations)

Petitioner: Power Grid Corporation of India Ltd. (PGCIL)
Respondents: UPPCL, BSPHCL, MPPMCL & other DISCOMs


Proceedings

  • PGCIL confirmed filing of all required information; pleadings completed; requested tariff approval
  • Respondents: None present except BSPHCL in Petition 408/TT/2024
  • Commission noted: Petition 59/TT/2025 – PGCIL failed to file information sought in RoP dated 20.06.2025

Commission’s Directions

Respondents: Final chance to file replies within 2 weeks; PGCIL may file rejoinder within 2 weeks thereafter

PGCIL (specific requirements):

  • 212/TT/2024: Reasons for delays (5–21 months) in supply of material for Assets 5, 6, 7
  • 284/TT/2024: Asset-wise details of time overrun due to shutdown issues (as per format)
  • 408/TT/2024: Justification of activity-wise time overrun (detailed format); time overrun due to RoW issues (detailed format); shutdown-related time overrun details (format); CEA Energization & Trial-run Certificates for Assets 1A, 5, 8
  • 59/TT/2025: Furnish missing information as directed in 20.06.2025 RoP

Outcome

  • Type of Order: Procedural (RoP)
  • Effect: Cases admitted; Commission seeking detailed time overrun justifications, energization certificates, and pending data before issuing tariff orders
  • Status: Orders reserved subject to compliance