Tender Summary – SJVN Ltd. (through SGEL)
Tender No.: SGEL/BD/1500 MW/RfS/0825
Date of Issue: 05 August 2025
Organisation: SJVN Green Energy Limited (SGEL), wholly owned subsidiary of SJVN Ltd.
Project: Selection of Solar Power Developers (SPDs) for setting up 1,500 MW ISTS-connected Solar PV Power Projects across India.
1. Scope of Work
- Setting up ISTS-connected Solar PV projects (50–750 MW per bidder).
- SPD to arrange land, connectivity, transmission up to ISTS, EPC, commissioning, and 25 years O&M.
- SGEL to enter into Power Purchase Agreement (PPA) for 25 years with successful bidders.
- Tariff to be discovered through competitive bidding followed by e-Reverse Auction.
2. Key Dates
- Tender Publication Date: 05.08.2025
- Pre-Bid Meeting: 19.08.2025
- Bid Submission Start: 05.08.2025
- Bid Submission End: 15.09.2025 (14:00 hrs)
- Technical Bid Opening: 15.09.2025 (14:30 hrs)
- Financial Bid Opening: To be notified for technically qualified bidders
- PPA Signing: Within 75 days of issue of LoA
3. Financial & Security Conditions
- EMD (Bid Security): ₹11,80,000 per MW (Bank Guarantee/online transfer, valid 9 months)
- Performance Bank Guarantee (PBG): ₹29,50,000 per MW, valid until commissioning + 1 year
- Tariff Ceiling: ₹2.95/kWh
- Bid Processing Fee: ₹5 lakh + 18% GST (non-refundable)
4. Eligibility Criteria
- Technical: No prior solar project experience required
- Financial:
- Net Worth: ≥ ₹1.06 crore/MW (as on 31.03.2025 or latest audited FY)
- Minimum Annual Turnover (MAT): ≥ ₹52.9 lakh/MW
- Internal Resource Generation (IRG): ≥ ₹10.6 lakh/MW
- In-principle sanction from lenders: ≥ 75% of debt requirement
- Bid Capacity: Minimum 50 MW, Maximum 750 MW per bidder
- Special Conditions:
- Only Class-I local suppliers (as per MII policy) allowed
- Consortium bidding permitted (max. 3 members); lead member must hold ≥ 51% shareholding
5. Bid Evaluation & Selection
- Process:
- Techno-commercial bid evaluation
- Financial bid opening of technically qualified bidders
- e-Reverse Auction (e-RA)
- Award: Lowest tariff (≤ ceiling) subject to meeting all eligibility & financial criteria
6. Commissioning Schedule
- 18 months from PPA signing – for projects requiring land acquisition/new transmission
- 15 months from PPA signing – if land & connectivity already in possession
- Part-commissioning allowed in blocks of 50 MW
7. Miscellaneous
- Change in Law: As per standard bidding guidelines, with pass-through benefits
- Extensions: SCOD extension possible for force majeure/transmission delays (up to 6 months)
- Penalties: For delay beyond SCOD, encashment of PBG + reduction in PPA tariff
8. Outcome
This tender invites bids for 1,500 MW ISTS solar capacity, with stringent financial criteria and local supplier conditions, aligned with SECI/NTPC-style national solar tenders.